Linear Vibration Welding of PE Pipes - 1998 [PE]

New Products & Site Techniques # 1998 Gothenburg

This paper describes an assessment of the quality of butt and branch joints in polyethylene (PE) pipes, produced using the linear vibration welding technique. Results showed that butt welds in pipes of 165 mm outside diameter(0D) could be produced within a total weld/cool time of 85 seconds, which is less than 15?'0 of the time required for butt fusion welding equivalent sized pipes in the field. The mechanical properties of the linear vibration welds were determined using tensile, impact and creep rupture tests. and results indicate that these joints are at least as good as current butt fusion welds. Pipe branches could also be made by the linear vibration technique by simply welding two pipes together at right angles. The resulting welds were stronger than the parent branch pipe. Based on these results, a prototype portable linear vibration welding machine has been developed in order to construct PE pipeline in the fields.

Please note that the whole article content is available on PPCA website onlySource : 1998 Gothenburg


Related papers

DEVELOPMENT OF FLAW ACCEPTANCE CRITERIA FOR WELDED JOINTS IN PE PIPES

Author(s) : Mike Troughton, Amir Khamsehnezhad 2016 Berlin

the inspection of butt fusion and electrofusion joints in polyethylene (PE) pipes. Depending on the technique and inspection procedure, various types of flaw, including discrete planar lack of fusion, particulate contamination, voids, cold fusions and pipe under-penetration can be detected. However, the usefulness of...

LATEST TECHNOLOGY OF SADDLE SCRAPER FOR POLYETHYLENE PIPE

Author(s) : Takehiro Fujii, Hideo Hirabayashi, Kazushi Yamada, Hiroyuki Nishimura 2016 Berlin

It is important to stabilize the scraped surface of the polyethylene pipe, even if some operator scrape the surface of the polyethylene pipe. In Japan this automatic saddle scraper is widely used for improving workability and plumbing quality The newly developed “Automatic saddle scraper” consists of the casing...

Development of an automated phased array ultrasonic inspection system and flaw acceptance criteria for welded joints in polyethylene pipes

Author(s) : Troughton Mike 2012 Barcelona

The current practice for assuring the quality of butt fusion and electrofusion welded joints during installation is by recording the welding parameters used, together with a visual inspection of the welded joint, supplemented by the destructive testing of welds on a sample basis using a short-term test. However,...

Comparison of Long-Term and Short-Term Tests for Electrofusion Joints in PE Pipes

Author(s) : Troughton, Brown, Hessel, Piovano 2006 Washington DC

As part of the Polytec Systems European-funded project, electrofusion (EF) joints in polyethylene (PE) pipe, containing different flaws, have been subjected to various standard and non-standard, long-term and short-term, coupon and whole pipe tests. The results were compared to determine which tests could discriminate...

Welding with Integrated Non-Destructive Examination of PE Pipes

Author(s) : Troughton 2001 Munich

This paper describes the development of an ultrasonic non-destructive examination (NDE) system that is incorporated into an automatic butt fusion welding machine and performs an examination of the joint within the cooling time of the welding cycle. The programme of work included the optimisation of the ultrasonic NDE...

Comparison of Short-Term Coupon Test

Author(s) : Hinchcliff, Troughton 1998 Gothenburg

There are a number of different mechanical test methods available to assess the quality of butt fusion welded joints in polyethylene (PE) pipes. However, little published information exists on the correlations that may or may not exist between the results from these methods. This paper compares the results from five...

High productivity butt fusion jointing of PE pipes

Author(s) : Cartwright, Troughton, Hinchcliff, Bowman, Jenkins 1995 Edinburgh

For the butt fusion joining of PE80 polyethylene pipes on site, long heat soak and cooling times predominate in the United Kingdom and other countries. The literature is reviewed to propose that these heat soak and cooling times can be significantly reduced via the use of machines with verifiable, reduced short...

Linear vibration welding of PE pipes - 1995

Author(s) : Troughton 1995 Edinburgh

This paper describes an initial programme of work to examine the feasibility of joining polyethylene pipe using the linear vibration welding technique. Commercial linear vibration welding equipment was used to join small lengths (100mm) of 125mm SDR11 PE80 and 180mm SDR17.6 PElOO pipe. Welds were achieved in total...

Members of the Association

BOREALISBOROUGEFormosa Plastics CorporationINEOS O&PIRPCKorea Petrochemical IND. Co., LTD (KPIC)LyondellBasellPetroChina Dushanzi Petrochemical CompanyPRIME POLYMERSABICSCG Chemicals & Thai PolyethyleneSinopecTASNEE
TOP